Construction Schedule

    January 2008 - Issuance of revised Master Use Permit by the City of Seattle
    April 2008 - Demolition of administrative building
    June 2008 - Completion of demolition
    August 2008 - Repair of Sanctuary building
    July 2014 - Shoring & Excavation will commence
    April 2015 - Complete Excavation and Erect Tower Crane
    May-August 2015 - Construct Building Foundations and Parking Garage Structure
    August 2015 - March 2017 - Construct Steel Office Tower Structure, Exterior Enclosures and Building Systems
    January 2016 - Rehabilitation of the Sanctuary building will commence
    October 2016 - Completion of the building and tenant move-in
    December 2016 - Opening of the hotel